The
Risk Maturity Model
The
UK MoD Defence Procurement Agency (DPA) commissioned
HVR to conduct a full programme of risk management
capability assessments for the Integrated Project
Teams (IPTs) responsible for its thirty major military
equipment acquisition projects. The total acquisition
value of these projects is approximately £60
billion. The projects affect all three armed services
and include Eurofighter, Bowman, CVF and the Astute
class submarines.
The
DPA had identified a need to measure risk management
capability when it recognised that project approvals
had been achieved on a number of projects on which
risk had subsequently proved to be too high. As a
result, the proportion of projects exceeding their
envelope of cost and/or schedule estimates was higher
than forecast. The implications were that either risks
were not being adequately managed following project
approval or that the risk assessments provided at
project approval decisions were not realistic.
The
HVR Risk Maturity Model was used to assess the risk
management capability of each IPT. These assessments
were used to identify and monitor improvements to
the DPA’s management of risk at both project
and “corporate” levels. It is now the
DPA’s policy that any project larger than £20
million must have a risk maturity level 3 capability
prior to seeking “Main Gate” approval.
